Posted on: September 14, 2022

City of Gainesville Mill and Overlay Project

The City of Gainesville will be conducting a mill and overlay program on several streets beginning on Monday September 19, 2022. The work will be done by Sunmount Paving at a cost of $2,012,340. The following is a tentative schedule of all of the streets involved with the project:

  • Morningside Dr. between S. Howeth St. and Line Dr. Sep. 19, 2022 to Oct. 13, 2022.
  • Locust St. between Harris St. and Jean St. Sep. 19, 2022 to Oct. 17, 2022.
  • Maplewood Dr. between Rosedale Dr. and Aspen Dr. Sep. 23, 2022 to Oct 17, 2022.
  • Cypress Ct. to Rosedale Dr. Sep. 29, to Oct. 19, 2022.
  • Aspen Rd. between Maplewood Dr. and Summa St. Oct. 3, 2022 to Nov. 17, 2022.
  • Greenbiar Ct. East of Aspen Rd. Oct. 22 to Nov. 30, 2022.
  • Everglade Ct. East of Aspen Rd. Nov. 3, 2022 to Dec. 21, 2022.
  • Fox Hollow & Quail Run to Bonner Rd. Dec. 8, 2022 and Jan. 9, 2023.
  • Dove Lane to Bonner Rd. Jan. 3, 2023 to Jan. 10, 2023.
  • Bonner Rd. from Cooke County Line to Quail Run. Jan. 12, 2023 to Feb. 1, 2023.
  • Bonner Rd. between Quail Run and W. California St. (FM 51) Feb. 2, 2023 to Feb. 24, 2023.

During the time of construction in your area, we ask that you do not park on the street as this will hinder the construction process. Thank you for your patience as we continue to improve our streets.

View the Contractor's Schedule (PDF)

Facebook Twitter Email

Other News in Home

Transfer Station Closure

Posted on: September 23, 2022
Notice of Road Closure

Notice of Sanitary Way Road Closure

Posted on: September 8, 2022

CITY COUNCIL ADOPTED TAX RATE

Posted on: September 8, 2022

Adopted Budget FY 2022-2023

Posted on: September 8, 2022